Configure per-project concurrency

Last updated on

Per-project concurrency allows you to define a concurrency limit independently for each project.

You can configure a Default Project Concurrency Limit that applies to every project and optionally configure a different Project Concurrency Limit Override for an individual project.

The account's total concurrency limit remains the maximum number of pipeline executions that can run concurrently across the entire account.

Per-project concurrency does not divide the account into High and Low priority partitions. Each project is evaluated against its own concurrency limit.

note

This feature is behind feature flags PIPE_PROJECT_LEVEL_EXECUTION_CONCURRENCY, PIPE_ENABLE_QUEUE_BASED_PLAN_CREATION, and PIPE_PER_PROJECT_CONCURRENCY_OVERRIDES. Contact Harness Support to enable the feature.


What will you learn in this topic?


Before you begin

  • Account administrator access: Only account administrators can configure the account-level default project concurrency settings. Go to RBAC in Harness to review role requirements.
  • Feature flags enabled: The per-project concurrency mode requires the PIPE_PROJECT_LEVEL_EXECUTION_CONCURRENCY, PIPE_ENABLE_QUEUE_BASED_PLAN_CREATION, and PIPE_PER_PROJECT_CONCURRENCY_OVERRIDES feature flags. Contact Harness Support if these flags are not enabled.

Configure the default project concurrency limit

To set the default concurrency limit for projects:

  1. Navigate to Account Settings > General > Default Settings > Pipeline > CONCURRENCY MANAGEMENT.

    Concurrency Management settings in per-project mode, showing the Default Project Concurrency Limit field
  2. In Concurrency Mode, select Set concurrency limits per project.

  3. Confirm the change when Harness prompts you. Changing the concurrency mode affects pipeline executions across the account.

  4. In Default Project Concurrency Limit, enter the concurrency limit that should apply to every project that does not have a project-specific override.

    The value must be a positive whole number and cannot exceed 100,000.

The default project concurrency limit applies to every project unless a project has a specific concurrency override.


Project-level overrides

You can optionally configure a different concurrency limit for an individual project.

To configure a different concurrency limit for an individual project:

  1. Navigate to Project Settings > General > Default Settings > Pipeline > CONCURRENCY MANAGEMENT.

    Project Default Settings showing the Project Concurrency Limit Override field under Concurrency Management
  2. In Project Concurrency Limit Override, enter the concurrency limit for the project.

  3. Leave the field empty to use the account-level default.

A project-specific concurrency override cannot exceed the account's total concurrency limit.

note

The Default Project Concurrency Limit is configured at the account scope and applies to projects that do not have an override.

The Project Concurrency Limit Override applies only to the project where it is configured.


Effective concurrency limits

Harness determines the effective concurrency limit for a project as follows:

  1. If the project has a Project Concurrency Limit Override, Harness uses that value.
  2. If the project does not have an override, Harness uses the Default Project Concurrency Limit configured at the account level.

The account's total concurrency limit remains the hard ceiling across all projects.

Project limits are independent limits. They do not reserve or divide the account's total concurrency capacity into separate partitions.


Execution behavior

When the number of running pipeline executions in a project reaches that project's concurrency limit, additional executions for that project are queued.

When the project falls below its concurrency limit, a queued execution starts automatically.

Harness displays the following message when a project reaches its concurrency limit:

Max number of concurrent executions reached for the project

note

Pipelines in Approval Pending status are excluded from the project concurrency limit.


Example

Consider an account with the following configuration:

  • Account total concurrency: 100
  • Default project concurrency: 10
  • Project A override: 30
  • Project B: no override

Project A can run up to 30 pipeline executions concurrently because it has a project-specific override.

Project B uses the account default and can run up to 10 executions concurrently.

Other projects without overrides also use the default limit of 10.

The account can never exceed 100 concurrent pipeline executions in total, regardless of the individual project limits.

If Project A reaches its limit of 30 executions, additional executions for Project A are queued. This does not prevent other projects from using their available concurrency.

note

The project concurrency limit controls the number of executions that can run concurrently within that project. The account-level concurrency limit continues to control the total number of concurrent executions across the account.